834 Divisadero St
San Francisco permit 201612165218 · Western Addition
Restaurant tenant improvement including kitchen & kitchen hood. change of occupancy from mercantile (m) to restaurant (a-2). ** maher: n/a **
- Filed
- Dec 16, 2016
- Issued
- Aug 21, 2017 (8 months after filing)
- Completed
- Jun 22, 2018 (10 months after issuance)
- Review stops
- 26 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 16, 2016 | Dec 16, 2016 | — |
Zoning review Planning · CP-ZOC | Dec 16, 2016 | Mar 28, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Feb 13, 2017 | Mar 28, 2017 | — |
Building plan review Building Inspection · BLDG | Apr 4, 2017 | Jun 20, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 11, 2017 | May 23, 2017 | — |
Fire prevention review Fire Department · SFFD | Jun 20, 2017 | Aug 10, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2017 | Jul 10, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2017 | Jul 26, 2017 | — |
Public health review Public Health · HEALTH | Jul 26, 2017 | Jul 28, 2017 | — |
Zoning review Planning · CP-ZOC | Aug 10, 2017 | Aug 14, 2017 | — |
Development fee collection Building Inspection · DFCU | Aug 15, 2017 | Aug 15, 2017 | — |
Permit Processing Center Building Inspection · PPC | Aug 15, 2017 | Aug 15, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2017 | Aug 21, 2017 | — |
Addendum 1: Archetectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 23, 2017 | Aug 23, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 23, 2017 | Aug 24, 2017 | — |
Electrical plan review Building Inspection · MECH-E | Aug 24, 2017 | Aug 24, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2017 | Sep 1, 2017 | — |
Electrical plan review Building Inspection · MECH-E | Sep 1, 2017 | Sep 1, 2017 | — |
Fire prevention review Fire Department · SFFD | Sep 1, 2017 | Sep 22, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Sep 14, 2017 | Sep 15, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2017 | Sep 19, 2017 | — |
Building plan review Building Inspection · BLDG | Sep 22, 2017 | Sep 22, 2017 | — |
Public health review Public Health · HEALTH | Sep 22, 2017 | Oct 2, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2017 | Oct 3, 2017 | — |
Permit Processing Center Building Inspection · PPC | Oct 3, 2017 | Oct 3, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2017 | Oct 6, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Zachary Joseph Maddry Dmarc Studio | Architect | C30718 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025