264 Grand View Av
San Francisco permit 201612195311 · Twin Peaks
Add 1 2-car 2-bike garage. renovate (e)bsmt& 1st level fl&replace(e)attic space w/ 2/fl living sapce. replace (e)non-code compliant stairs w/ cope compliant stairs. replace failed retaining wall at back yard re-finish back yard peck w/ wood tiles.
- Filed
- Dec 19, 2016
- Issued
- Nov 1, 2018 (22 months after filing)
- Completed
- Jan 20, 2023 (51 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 23, 2017 | Jun 23, 2017 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2017 | Jul 17, 2018 | — |
Planning neighborhood notice Planning · CP-NP | May 31, 2018 | Jul 11, 2018 | — |
Building plan review Building Inspection · BLDG | Jul 18, 2018 | Aug 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Aug 9, 2018 | Aug 10, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2018 | Sep 19, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 18, 2018 | Sep 26, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 28, 2018 | Sep 28, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2018 | Oct 2, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2018 | Oct 3, 2018 | — |
Development fee collection Building Inspection · DFCU | Oct 4, 2018 | Oct 4, 2018 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2018 | Oct 4, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2018 | Nov 1, 2018 | — |
Addendum 1: Superstructure,t24,arch, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 20, 2018 | Nov 20, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 20, 2018 | Mar 22, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 10, 2019 | Mar 14, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2019 | Apr 12, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2019 | Feb 11, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2019 | Apr 17, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 18, 2019 | Apr 22, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 22, 2019 | Apr 22, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2019 | Apr 25, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Yoo Ju No | Architect | C34390 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025