San Francisco permit 201612195336 · Bayview Hunters Point
Remove & replace metal roof.new free-standing offices&support rms for mta overhead lines¢ral warehouse operations.demo&replace concrete slab thru-out w/ new structural slab, strengthen (e) steel frames. new plumbing layout, new electral lighting & power distribution, new fire protection sys.
- Filed
- Dec 19, 2016
- Issued
- Jul 24, 2017 (7 months after filing)
- Completed
- Sep 1, 2020 (37 months after issuance)
- Review stops
- 25 stops across 7 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Disability access review Mayor's Office on Disability · MOD | Dec 19, 2016 | Dec 19, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2016 | Dec 22, 2016 | — |
Zoning review Planning · CP-ZOC | Dec 27, 2016 | Mar 31, 2017 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2017 | Apr 13, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2017 | Apr 17, 2017 | — |
Fire prevention review Fire Department · SFFD | Apr 17, 2017 | Jun 29, 2017 | — |
Street use and mapping Public Works · DPW-BSM | May 26, 2017 | May 30, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2017 | Jun 14, 2017 | — |
Public health review Public Health · HEALTH | Jun 29, 2017 | Jul 10, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jul 12, 2017 | Jul 13, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jul 13, 2017 | Jul 24, 2017 | — |
Addendum 1: Demolition/structural/civil
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 31, 2017 | Jul 31, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 31, 2017 | Aug 10, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2017 | Nov 17, 2017 | — |
Permit Processing Center Building Inspection · PPC | Nov 22, 2017 | Nov 22, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2017 | Dec 5, 2017 | — |
Addendum 2: Mech/electrical/plumbing/fire protection/ arch
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 31, 2017 | Jul 31, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 31, 2017 | Aug 21, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2017 | Jan 12, 2018 | — |
Fire prevention review Fire Department · SFFD | Jul 31, 2017 | Feb 2, 2018 | — |
Electrical plan review Building Inspection · MECH-E | Aug 11, 2017 | Jan 9, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2017 | Jan 29, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2017 | Oct 2, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 2, 2018 | Feb 7, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2018 | Feb 21, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $26,000,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Joseph Maloney Dpw/Bureau Of Architecture | Architect | C-16935 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026