2918 Mission St
San Francisco permit 201612285987 · Mission
To erect 8 stories, no basement, type iii-a (5 story) / i-a, 75 (3 story) residential units with retail mixed use building. (r-2,m) building on block 6529, lot 002, 002a & 003. ** maher: exempt - approval letter from dph attached **
- Filed
- Dec 28, 2016
- Issued
- Nov 13, 2018 (23 months after filing)
- Completed
- Not completed yet
- Review stops
- 101 stops across 7 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Fire Department, Public Works
- Put on hold
- 11 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2016 | Dec 29, 2016 | — |
Zoning review Planning · CP-ZOC | Dec 29, 2016 | Oct 30, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 28, 2017 | May 11, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 17, 2018 | May 22, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jan 19, 2018 | Jun 6, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2018 | Feb 21, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2018 | May 24, 2018 | — |
Development fee collection Building Inspection · DFCU | Jun 8, 2018 | Nov 2, 2018 | — |
Zoning review Planning · CP-ZOC | Jun 11, 2018 | Oct 30, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 30, 2018 | Oct 31, 2018 | — |
Fire prevention review Fire Department · SFFD | Oct 31, 2018 | Oct 31, 2018 | — |
Permit Processing Center Building Inspection · PPC | Oct 31, 2018 | Nov 5, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Nov 5, 2018 | Nov 13, 2018 | — |
Addendum 1: Foundation, structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 11, 2020 | Jul 11, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 14, 2020 | Mar 24, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2021 | Apr 8, 2021 | — |
Permit Processing Center Building Inspection · PPC | Apr 9, 2021 | Apr 9, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2021 | Nov 15, 2021 | — |
Addendum 2: Architectural / mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 26, 2020 | Aug 26, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 26, 2020 | Aug 25, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2020 | Dec 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 26, 2020 | Dec 16, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2020 | Jan 25, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Jan 25, 2021 | Nov 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2021 | Aug 31, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 31, 2021 | Sep 10, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 4, 2022 | Dec 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2022 | May 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 21, 2022 | Apr 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2023 | May 10, 2023 | — |
Zoning review Planning · CP-ZOC | May 18, 2023 | Dec 13, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 15, 2023 | Dec 15, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 19, 2023 | Dec 19, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2023 | Dec 20, 2023 | Administrative |
Addendum 3: Stormwater.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 8, 2020 | Oct 8, 2020 | — |
Plumbing plan check Building Inspection · PID-PC | Oct 9, 2020 | Feb 18, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jan 18, 2022 | Jan 20, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 20, 2022 | Jan 26, 2022 | — |
Addendum 4: Fire sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 29, 2026 | Nov 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2026 | Nov 4, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Nov 4, 2026 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 4, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 10: Rev1 to issued addendum 1 (foundation / superstructure)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2026 | Mar 3, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 25, 2026 | Apr 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2026 | Apr 2, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 2, 2026 | Apr 11, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Apr 2, 2026 | Apr 11, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2026 | Apr 15, 2026 | Approved |
Public Health HEALTH-MH | Apr 2, 2026 | Apr 14, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 2, 2026 | Jun 29, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 9, 2026 | Jun 26, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 9, 2026 | Jun 11, 2026 | Approved |
Public Health HEALTH-MH | Jun 9, 2026 | Jun 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 29, 2026 | Jun 30, 2026 | Administrative |
Addendum 11: Rev 1 to issued addendum 2 (architectural /mep)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2026 | Mar 3, 2026 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2026 | Apr 10, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Mar 27, 2026 | Apr 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2026 | Apr 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2026 | Jun 5, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2026 | Apr 21, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2026 | Apr 21, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 22, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2026 | Apr 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 10, 2026 | May 30, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2026 | Apr 21, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 10, 2026 | May 8, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | Apr 10, 2026 | May 28, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 10, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | May 20, 2026 | In progress | In Progress |
Zoning review Planning · CP-ZOC | Jul 1, 2026 | Jul 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2026 | Jul 15, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2026 | Jul 17, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 1, 2026 | Jul 22, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 1, 2026 | Jul 7, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 1, 2026 | Jul 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2026 | Jul 14, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 1, 2026 | Jul 17, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | Jul 1, 2026 | Sep 21, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 22, 2026 | Oct 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 22, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2026 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Oct 22, 2026 | Nov 4, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 22, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 22, 2026 | Oct 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 22, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 22, 2026 | Oct 29, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Oct 22, 2026 | Oct 23, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | Oct 22, 2026 | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 12: Wood tie-down system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 19, 2026 | Apr 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2026 | Apr 7, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 7, 2026 | Apr 25, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 7, 2026 | Apr 25, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Apr 7, 2026 | Apr 11, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Apr 7, 2026 | Jul 8, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 23, 2026 | Jul 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2026 | Jul 13, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $15,000,000
| Name | Role | License on permit |
|---|---|---|
| Robert Mark Baum Gould Evans Baum Thornley | Architect | C12094 |
| Jordan Elling Hague Dci Engineers | Engineer | S6509 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026