179 Castro St
San Francisco permit 201612296248 · Castro/Upper Market
Renovation of unoccupied level for addition of (2) adu's; work includes lowering of level 1, stair modifications, addition of kitchens & bathrooms, minor window modificaiton, removal & replacement of interior partitions, doors & finishes. sprinkler/alarm deferred.
- Filed
- Dec 29, 2016
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 30, 2016 | Dec 30, 2016 | — |
Zoning review Planning · CP-ZOC | Dec 30, 2016 | Jul 7, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2017 | Aug 29, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2017 | Nov 2, 2017 | — |
Fire prevention review Fire Department · SFFD | Sep 1, 2017 | Nov 2, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Oct 26, 2017 | Oct 30, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2017 | Nov 1, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2017 | Dec 1, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 6, 2017 | Jan 24, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jan 24, 2018 | Jan 24, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jan 24, 2018 | Apr 10, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Withdrawn
- Estimated cost
- $208,000
| Name | Role | License on permit |
|---|---|---|
| Elizabeth Berrien Morris Beth Morris Architecture Inc | Architect | C29516 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026