363 06th St
San Francisco permit 201702280331 · South of Market
To erect 9 stories, no basement, type i-a, 104 residential units wtih commercial & garage building. ** maher: yes. please route to dph **
- Filed
- Feb 28, 2017
- Issued
- Oct 11, 2017 (7 months after filing)
- Completed
- Nov 3, 2020 (37 months after issuance)
- Review stops
- 49 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 12 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 1, 2017 | Mar 1, 2017 | — |
Zoning review Planning · CP-ZOC | Mar 1, 2017 | May 15, 2017 | — |
Building plan review Building Inspection · BLDG | May 16, 2017 | Jun 1, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2017 | Jun 20, 2017 | — |
Fire prevention review Fire Department · SFFD | Jun 20, 2017 | Sep 22, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2017 | Aug 9, 2017 | — |
Public health review Public Health · HEALTH | Sep 22, 2017 | Oct 3, 2017 | — |
Development fee collection Building Inspection · DFCU | Oct 3, 2017 | Oct 10, 2017 | — |
Permit Processing Center Building Inspection · PPC | Oct 3, 2017 | Oct 10, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2017 | Oct 11, 2017 | — |
Addendum 1: Foundation.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 17, 2017 | Oct 17, 2017 | — |
Building plan review Building Inspection · BLDG | Oct 17, 2017 | Feb 5, 2018 | — |
Development fee collection Building Inspection · DFCU | Jan 12, 2018 | Jan 12, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2018 | Jan 22, 2018 | — |
Permit Processing Center Building Inspection · PPC | Feb 5, 2018 | Feb 5, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2018 | Mar 16, 2018 | — |
Addendum 2: Superstructure framing.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 23, 2020 | Sep 23, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 23, 2020 | Sep 23, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 23, 2020 | Sep 23, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2020 | Sep 23, 2020 | — |
Addendum 3: Architectural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 14, 2017 | Dec 14, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 14, 2017 | Jan 16, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2018 | Nov 7, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 29, 2018 | Sep 13, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2018 | Dec 14, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2018 | Jul 21, 2018 | — |
Public health review Public Health · HEALTH | Nov 7, 2018 | Nov 14, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 17, 2018 | Dec 26, 2018 | — |
Permit Processing Center Building Inspection · PPC | Dec 26, 2018 | Dec 26, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Dec 26, 2018 | Dec 27, 2018 | — |
Addendum 4: Mechanical & electrical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 16, 2018 | Nov 16, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2018 | Feb 27, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Dec 10, 2018 | Apr 12, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 7, 2019 | Jan 7, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 12, 2019 | Apr 12, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2019 | Apr 15, 2019 | — |
Addendum 5: Fire sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 8, 2019 | Feb 8, 2019 | — |
Fire prevention review Fire Department · SFFD | Feb 8, 2019 | Apr 3, 2019 | — |
Fire prevention review Fire Department · SFFD | Apr 4, 2019 | Apr 5, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 4, 2019 | Apr 5, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 5, 2019 | Apr 9, 2019 | — |
Addendum 6: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 21, 2020 | Sep 15, 2020 | — |
Fire prevention review Fire Department · SFFD | May 21, 2020 | Sep 14, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jul 27, 2020 | Sep 15, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2020 | Sep 16, 2020 | — |
Addendum 7: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 8, 2020 | Jan 8, 2020 | — |
Fire prevention review Fire Department · SFFD | Jan 9, 2020 | Jan 30, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 30, 2020 | Jan 30, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2020 | Sep 18, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $17,893,508
| Name | Role | License on permit |
|---|---|---|
| Siavash Tahbazof Sia Consulting | Engineer | C38827 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026