739 De Haro St
San Francisco permit 201703070898 · Potrero Hill
Remodel of an (e) single family home with a new 2nd floor addition & garage. 1 new bedroom & 1 new bathroom. upgrade of mechanical, electrical & structural systems. addition of new fire sprinkler system.
- Filed
- Mar 7, 2017
- Issued
- Oct 30, 2018 (20 months after filing)
- Completed
- Not completed yet
- Review stops
- 28 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 8, 2017 | Mar 8, 2017 | — |
Zoning review Planning · CP-ZOC | Mar 10, 2017 | May 18, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Dec 19, 2017 | Feb 1, 2018 | — |
Planning discretionary review Planning · CP-DR | Feb 15, 2018 | May 18, 2018 | — |
Building plan review Building Inspection · BLDG | May 21, 2018 | Sep 6, 2018 | — |
Fire prevention review Fire Department · SFFD | Jun 27, 2018 | Aug 22, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2018 | Sep 10, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2018 | Sep 28, 2018 | — |
Fire prevention review Fire Department · SFFD | Oct 3, 2018 | Oct 12, 2018 | — |
Permit Processing Center Building Inspection · PPC | Oct 3, 2018 | Oct 17, 2018 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2018 | Oct 16, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2018 | Oct 30, 2018 | — |
Addendum 1: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 14, 2019 | Feb 14, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 14, 2019 | Feb 21, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 21, 2019 | Mar 8, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 8, 2019 | Jun 3, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2019 | Jul 9, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2019 | Jul 10, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jul 10, 2019 | Jul 12, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jul 12, 2019 | In progress | — |
Addendum 2: Mechanical, architectural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 20, 2019 | Feb 20, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 20, 2019 | Jul 18, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2019 | May 10, 2019 | — |
Fire prevention review Fire Department · SFFD | May 10, 2019 | Jun 7, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jun 7, 2019 | Jul 22, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2019 | Jun 19, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jul 23, 2019 | Jul 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2019 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| Anne Noelle Fougeron Fougeron Architecture | Architect | 18901 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025