174 Hearst Av
San Francisco permit 201704053200 · West of Twin Peaks
The proposal is to add a bedroom, bathroom, kitchen/dining area, open staircase & basement workroom by making a horizontal extension of 19 feet to the rear of the house. excavation of the basement will provide space for new storage/utility area.
- Filed
- Apr 5, 2017
- Issued
- Feb 22, 2018 (11 months after filing)
- Completed
- Jan 2, 2020 (22 months after issuance)
- Review stops
- 20 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 5, 2017 | Apr 5, 2017 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2017 | Sep 27, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Aug 4, 2017 | Sep 27, 2017 | — |
Building plan review Building Inspection · BLDG | Sep 28, 2017 | Dec 6, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Nov 15, 2017 | Nov 17, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2017 | Dec 5, 2017 | — |
Zoning review Planning · CP-ZOC | Dec 8, 2017 | Jan 16, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jan 17, 2018 | Jan 18, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 19, 2018 | Jan 19, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jan 22, 2018 | Jan 22, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jan 22, 2018 | Feb 22, 2018 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 9, 2018 | Apr 9, 2018 | — |
Building plan review Building Inspection · BLDG | Apr 9, 2018 | Apr 23, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 23, 2018 | Apr 23, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2018 | Apr 23, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2018 | Apr 25, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2018 | Apr 30, 2018 | — |
Building plan review Building Inspection · BLDG | May 1, 2018 | May 1, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 1, 2018 | May 1, 2018 | — |
Central Permit Bureau Building Inspection · CPB | May 1, 2018 | Jul 24, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Thornton Weiler Thornton Weiler Aia | Architect | C27685 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2014