506 Molimo Dr
San Francisco permit 201704103570 · West of Twin Peaks
New decks @ basement, 1st & 2nd floors. new spiral stair from 1st floor deck to 2nd floor deck. new exterior stair from 1st floor deck to grade. interior remodel includes kitchen, 1st floor, hallway, rear window & door replacement. basement development for media room & powder room.
- Filed
- Apr 10, 2017
- Issued
- Feb 5, 2018 (10 months after filing)
- Completed
- Sep 13, 2019 (19 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2017 | Apr 14, 2017 | — |
Zoning review Planning · CP-ZOC | Apr 14, 2017 | Aug 18, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Aug 18, 2017 | Oct 2, 2017 | — |
Building plan review Building Inspection · BLDG | Oct 3, 2017 | Oct 30, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2017 | Nov 1, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2017 | Nov 20, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 5, 2018 | Feb 5, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2018 | Feb 5, 2018 | — |
Addendum 1: Superstructure,t24,mech,ele,mech,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 26, 2018 | Feb 26, 2018 | — |
Building plan review Building Inspection · BLDG | Feb 26, 2018 | Apr 13, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2018 | Mar 26, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Mar 26, 2018 | May 14, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 30, 2018 | Apr 2, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2018 | May 15, 2018 | — |
Central Permit Bureau Building Inspection · CPB | May 15, 2018 | Sep 27, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $125,000
| Name | Role | License on permit |
|---|---|---|
| Roxanna C Rivera Cmd Architecture | Authorized agent-others | C32959 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025