166 Park St
San Francisco permit 201704133909 · Bernal Heights
Horizontal add.rear addition/remodel/convert(e) lower floor storage(e)2 story bldg into new res'l dwg incl:remove rear portion of(e)bldg at lower floor&upper floor,(n)rear addition at lower & upper floor; create(n)1 car garage at lower fl,rescope(e)driveway access to the(n)garage create(n)2 bedrms..
- Filed
- Apr 13, 2017
- Issued
- Jul 16, 2018 (15 months after filing)
- Completed
- Oct 13, 2022 (51 months after issuance)
- Review stops
- 30 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 9 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 26, 2017 | Apr 26, 2017 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2017 | Mar 19, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Dec 7, 2017 | Mar 19, 2018 | — |
Building plan review Building Inspection · BLDG | Mar 20, 2018 | Jun 14, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2018 | Jun 19, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2018 | May 3, 2018 | — |
Zoning review Planning · CP-ZOC | Jun 22, 2018 | Jun 22, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jun 25, 2018 | Jun 25, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2018 | Jul 16, 2018 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 13, 2018 | Nov 13, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 13, 2018 | Nov 14, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 14, 2018 | Nov 30, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 30, 2018 | Dec 4, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2018 | Jun 12, 2019 | — |
Development fee collection Building Inspection · DFCU | Dec 14, 2018 | Dec 14, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jun 13, 2019 | Jun 13, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2019 | Jun 18, 2019 | — |
Addendum 2: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 12, 2020 | Nov 12, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 12, 2020 | Mar 31, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2021 | Jun 22, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 23, 2021 | Jun 23, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 23, 2021 | Jul 2, 2021 | — |
Addendum 3: Architectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 12, 2020 | Nov 12, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 12, 2020 | Mar 31, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2021 | Jun 3, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2021 | Jun 15, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2021 | Jul 2, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2021 | Jul 15, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jul 15, 2021 | Jul 15, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jul 15, 2021 | Jul 26, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Yogesh Chitlangia Yogesh Chitlangia Architect | Architect | C31132 |
| David W Kane Harrell Kane S.E. Inc. | Engineer | S-5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026