4495 Mission St
San Francisco permit 201705025401 · Excelsior
Change of use. t.i: remove (e) restroom & water heater. new accessible restroom, employee locker rooms, dishwashing room & dry storage room. new secondary storage mezzanine. new serving counter and coffee prep area.
- Filed
- May 2, 2017
- Issued
- Nov 28, 2017 (7 months after filing)
- Completed
- May 13, 2019 (17 months after issuance)
- Review stops
- 20 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 2, 2017 | May 2, 2017 | — |
Zoning review Planning · CP-ZOC | May 2, 2017 | Jul 20, 2017 | — |
Fire prevention review Fire Department · SFFD | May 2, 2017 | May 2, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Jun 7, 2017 | Jul 20, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 21, 2017 | Aug 9, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 9, 2017 | Aug 21, 2017 | — |
Public health review Public Health · HEALTH | Aug 18, 2017 | Aug 24, 2017 | — |
Development fee collection Building Inspection · DFCU | Aug 25, 2017 | Aug 25, 2017 | — |
Permit Processing Center Building Inspection · PPC | Aug 25, 2017 | Aug 25, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2017 | Oct 19, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 20, 2017 | Oct 20, 2017 | — |
Permit Processing Center Building Inspection · PPC | Oct 20, 2017 | Oct 20, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2017 | Nov 28, 2017 | — |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 4, 2017 | Dec 4, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 5, 2017 | Mar 12, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 4, 2018 | Jan 25, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2018 | Jan 26, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2018 | Mar 12, 2018 | — |
Permit Processing Center Building Inspection · PPC | Mar 16, 2018 | Mar 16, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2018 | Mar 16, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Ian R Dunn Openscope Studio | Architect | C-27241 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025