198 Potrero Av
San Francisco permit 201705045698 · Mission
Change of use from restaurant(partial 2nd fl) to legitimize (e) office. exterior upgrades, demo include remove exterior door, fire escape, sidewalk, roof, deck & stair, skylights. accessible entrance, service door, deck, stair & rr upgrade strengthen roof frame. (2nd fl occupied, 1st & mez
- Filed
- May 4, 2017
- Issued
- Jun 18, 2018 (13 months after filing)
- Completed
- Sep 14, 2020 (27 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 4, 2017 | May 4, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2017 | Nov 14, 2017 | — |
Zoning review Planning · CP-ZOC | Nov 15, 2017 | Nov 27, 2017 | — |
Building plan review Building Inspection · BLDG | Nov 28, 2017 | Jan 8, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2017 | Dec 22, 2017 | — |
Building plan review Building Inspection · BLDG | Jan 8, 2018 | Jan 24, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 30, 2018 | Jan 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2018 | May 7, 2018 | — |
Fire prevention review Fire Department · SFFD | May 8, 2018 | May 10, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 10, 2018 | May 10, 2018 | — |
Central Permit Bureau Building Inspection · CPB | May 10, 2018 | May 22, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2018 | Jun 1, 2018 | — |
Development fee collection Building Inspection · DFCU | Jun 1, 2018 | Jun 4, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jun 1, 2018 | Jun 4, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2018 | Jun 18, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Pamela Robinson Smithgroup | Architect | C-25429 |
| Brian R Neumann Neumann Sloat Blanco Arch | Architect | C-27038 |
| Ben Au Holmes Culley | Engineer | S4938 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025