993 Mission St
San Francisco permit 201705116406 · South of Market
Expansion of (e) bar/night club at 101 6th st to convert an (e)pawn shop. change of use to restaurant under 50 occupants. will include interior demo & construction, ada upgrades. work includes ground flr. dining/kit & kit/stor @ basement. 993 mission st as separate address for
- Filed
- May 11, 2017
- Issued
- May 25, 2018 (12 months after filing)
- Completed
- Dec 19, 2018 (7 months after issuance)
- Review stops
- 22 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 15, 2017 | May 15, 2017 | — |
Zoning review Planning · CP-ZOC | May 15, 2017 | Nov 6, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Sep 8, 2017 | Mar 22, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2017 | Mar 13, 2018 | — |
Zoning review Planning · CP-ZOC | Mar 26, 2018 | Mar 26, 2018 | — |
Fire prevention review Fire Department · SFFD | Mar 27, 2018 | Apr 9, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 9, 2018 | Apr 10, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 11, 2018 | Apr 27, 2018 | — |
Public health review Public Health · HEALTH | Apr 27, 2018 | May 3, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 3, 2018 | May 3, 2018 | — |
Central Permit Bureau Building Inspection · CPB | May 3, 2018 | May 25, 2018 | — |
Development fee collection Building Inspection · DFCU | May 11, 2018 | May 11, 2018 | — |
Addendum 1: Struct,arch,t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 5, 2018 | Jun 5, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 6, 2018 | Jul 13, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 7, 2018 | Jul 17, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 13, 2018 | Jul 20, 2018 | — |
Electrical plan review Building Inspection · MECH-E | Jul 20, 2018 | Jul 25, 2018 | — |
Fire prevention review Fire Department · SFFD | Jul 25, 2018 | Aug 3, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2018 | Aug 8, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 9, 2018 | Aug 9, 2018 | — |
Permit Processing Center Building Inspection · PPC | Aug 10, 2018 | Aug 10, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2018 | Aug 14, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Benjamin Clifford Anderson Anderson Studio For Arch. | Architect | C31274 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2025