1232 Sanchez St
San Francisco permit 201706129056 · Noe Valley
Site permit below -adjacent -grade addition @ basement level (e) staircase removed. rebuild compliant (n) staircase from basement to backyard.
- Filed
- Jun 12, 2017
- Issued
- Aug 15, 2018 (14 months after filing)
- Completed
- Jul 20, 2021 (35 months after issuance)
- Review stops
- 17 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 12, 2017 | Jun 12, 2017 | — |
Zoning review Planning · CP-ZOC | Jun 13, 2017 | Feb 27, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Jun 28, 2017 | Feb 27, 2018 | — |
Building plan review Building Inspection · BLDG | Feb 28, 2018 | Jul 12, 2018 | — |
Zoning review Planning · CP-ZOC | Jul 12, 2018 | Jul 27, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jul 30, 2018 | Jul 30, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2018 | Aug 1, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2018 | Aug 9, 2018 | — |
Permit Processing Center Building Inspection · PPC | Aug 10, 2018 | Aug 10, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2018 | Aug 15, 2018 | — |
Addendum 1: Struc,mech, arch, t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 17, 2018 | Aug 17, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 17, 2018 | Sep 20, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 17, 2018 | Feb 22, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2019 | Feb 26, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 31, 2019 | Feb 14, 2019 | — |
Permit Processing Center Building Inspection · PPC | Feb 26, 2019 | Feb 26, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2019 | Mar 1, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| James David Whitfield Whitfield Architects | Architect | C-31997 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022