354 27th Av
San Francisco permit 201706129077 · Outer Richmond
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa #2015-0420-4070. interior layout revisions, radiant heating replaced with gas furnaces, 1st flr lowered 1 foot. no change to maximum excavation depth, minor window configuration revisions - rear facade only.
- Filed
- Jun 12, 2017
- Issued
- Sep 12, 2017 (3 months after filing)
- Completed
- Jun 4, 2018 (9 months after issuance)
- Review stops
- 10 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 12, 2017 | Jun 12, 2017 | — |
Zoning review Planning · CP-ZOC | Jun 13, 2017 | Jul 10, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2017 | Aug 11, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2017 | Sep 5, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2017 | Aug 25, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2017 | Aug 30, 2017 | — |
Zoning review Planning · CP-ZOC | Sep 6, 2017 | Sep 7, 2017 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2017 | Sep 11, 2017 | — |
Permit Processing Center Building Inspection · PPC | Sep 11, 2017 | Sep 11, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2017 | Sep 12, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Abraham Jayson Jayson Architecture | Architect | C33239 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2015