81 05th Av
San Francisco permit 201707111562 · Inner Richmond
Enlarge & remodel interior of (e) all floors. enlarge gable roof towards rear. (n) & enlarged dormers. (n) roof deck at 2nd flr.
- Filed
- Jul 11, 2017
- Issued
- Apr 18, 2018 (9 months after filing)
- Completed
- Dec 11, 2020 (32 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 12, 2017 | Jul 12, 2017 | — |
Zoning review Planning · CP-ZOC | Jul 12, 2017 | Feb 24, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Dec 27, 2017 | Feb 24, 2018 | — |
Building plan review Building Inspection · BLDG | Feb 26, 2018 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Mar 13, 2018 | Mar 14, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2018 | Mar 21, 2018 | — |
Zoning review Planning · CP-ZOC | Mar 30, 2018 | Apr 2, 2018 | — |
Permit Processing Center Building Inspection · PPC | Mar 30, 2018 | Apr 6, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2018 | Apr 4, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 5, 2018 | Apr 6, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Apr 6, 2018 | Apr 18, 2018 | — |
Addendum 1: Foundation.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 14, 2018 | May 14, 2018 | — |
Building plan review Building Inspection · BLDG | May 14, 2018 | Jun 22, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2018 | Jun 28, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jun 28, 2018 | Jun 28, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jun 28, 2018 | Jul 5, 2018 | — |
Addendum 2: Arch / superstructure / t-24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 6, 2018 | Aug 6, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 6, 2018 | Oct 11, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2018 | Sep 25, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2018 | Sep 26, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2018 | Oct 17, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2018 | Oct 17, 2018 | — |
Permit Processing Center Building Inspection · PPC | Oct 18, 2018 | Oct 18, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Oct 18, 2018 | Oct 18, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $837,200
| Name | Role | License on permit |
|---|---|---|
| John Patrick Maniscalco John Maniscalco Architecture | Architect | C25148 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2014