20 Raycliff Tr
San Francisco permit 201708114666 · Pacific Heights
Remodel (e) 2-story bldg including expansion of basement & addition of 3rd story w/ roof deck - total of (4) bedroom s & (3 1/2) bathrooms.
- Filed
- Aug 11, 2017
- Issued
- Apr 5, 2019 (20 months after filing)
- Completed
- Jun 3, 2022 (38 months after issuance)
- Review stops
- 27 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 11, 2017 | Aug 11, 2017 | — |
Zoning review Planning · CP-ZOC | Aug 14, 2017 | Aug 14, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 14, 2017 | Sep 6, 2017 | — |
Zoning review Planning · CP-ZOC | Sep 6, 2017 | Dec 14, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Sep 20, 2018 | Dec 14, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 17, 2018 | Mar 7, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jan 15, 2019 | Jan 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2019 | Feb 19, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Mar 8, 2019 | Mar 11, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 12, 2019 | Mar 14, 2019 | — |
Zoning review Planning · CP-ZOC | Mar 15, 2019 | Mar 21, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 22, 2019 | Apr 4, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 4, 2019 | Apr 4, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 4, 2019 | Apr 5, 2019 | — |
Addendum 1: Foundation for demo, excavation, retaining walls & structural foundation include concrete work.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 11, 2019 | Apr 11, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 11, 2019 | Jun 3, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2019 | Jun 13, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jun 14, 2019 | Jun 14, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 14, 2019 | Jun 14, 2019 | — |
Addendum 2: Super structure for all above grade framing, arch, mep, exterior envelop & all interior finishes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 7, 2019 | Jun 7, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 7, 2019 | Jul 19, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2019 | Aug 15, 2019 | — |
Fire prevention review Fire Department · SFFD | Jul 25, 2019 | Aug 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2019 | Aug 13, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2019 | Aug 19, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 19, 2019 | Aug 19, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2019 | Aug 20, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,120,000
| Name | Role | License on permit |
|---|---|---|
| Jon Eric Brody Jon Brody Structural Engineers | Engineer | S4518 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015