3230 24th St
San Francisco permit 201708154803 · Mission
To erect 5 stories, no basement, type va over type ia, 17 units residential over commercial building.(r-2,m,b) lot #011a & 015
- Filed
- Aug 15, 2017
- Issued
- Feb 25, 2020 (30 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 9 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 16, 2017 | Aug 16, 2017 | — |
Zoning review Planning · CP-ZOC | Aug 16, 2017 | Nov 1, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Aug 6, 2018 | Nov 1, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2018 | Dec 4, 2019 | — |
Fire prevention review Fire Department · SFFD | Dec 5, 2018 | Dec 18, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2018 | Jan 2, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 3, 2019 | Mar 11, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2019 | Dec 20, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2019 | Dec 30, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 30, 2019 | Jan 2, 2020 | — |
Development fee collection Building Inspection · DFCU | Jan 3, 2020 | Jan 22, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 3, 2020 | Jan 22, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 22, 2020 | Feb 25, 2020 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2020 | Mar 9, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2020 | May 7, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2020 | Oct 7, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Oct 7, 2020 | Mar 21, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2023 | Mar 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 27, 2023 | Mar 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2023 | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Addendum 2: Architectural,superstructure,mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 24, 2020 | Aug 24, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 24, 2020 | Jan 6, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2021 | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Cancelled
- Estimated cost
- $4,500,000
| Name | Role | License on permit |
|---|---|---|
| Lev H Weisbach Weisbach Architecture | Architect | C22099 |
| David W Kane Harrell Kane Struct Enginee | Engineer | 5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022