313 Castro St
San Francisco permit 201708185277 · Castro/Upper Market
Convert (e) 1st floor to a 2nd unit. add 2 bedrooms, 1 bathroom, kitchen, living area & dining area in the 1st floor.
- Filed
- Aug 18, 2017
- Issued
- Feb 12, 2018 (6 months after filing)
- Completed
- Not completed yet
- Review stops
- 16 stops across 4 departments
- Comments issued
- None
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 28, 2017 | Aug 28, 2017 | — |
Zoning review Planning · CP-ZOC | Aug 28, 2017 | Dec 5, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 6, 2017 | Dec 20, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Dec 21, 2017 | Dec 22, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2017 | Jan 17, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jan 17, 2018 | Feb 2, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2018 | Feb 12, 2018 | — |
Addendum 1: Struct,arch,mech,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 4, 2018 | Apr 4, 2018 | — |
Building plan review Building Inspection · BLDG | Apr 4, 2018 | Apr 12, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 12, 2018 | Apr 12, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2018 | Apr 17, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 17, 2018 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2018 | Jun 12, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2018 | Jun 14, 2018 | — |
Permit Processing Center Building Inspection · PPC | Mar 5, 2024 | Jul 5, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $70,000
| Name | Role | License on permit |
|---|---|---|
| Scott Cibotti Cibotti Engineering | Engineer | C62912 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022