630 Precita Av
San Francisco permit 201708235716 · Bernal Heights
Add (n) unit. 1st unit on 1st fl & 2nd unit on 2nd & 3rd fl. horizontal addition on 1st & 2nd fl. vertical addition - 3rd fl. complete interior remodel. demolish (e) floor framing on 2nd fl. windows replacement all sides.
- Filed
- Aug 23, 2017
- Issued
- May 17, 2019 (21 months after filing)
- Completed
- Not completed yet
- Review stops
- 21 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 24, 2017 | Aug 24, 2017 | — |
Zoning review Planning · CP-ZOC | Aug 24, 2017 | May 22, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Mar 20, 2018 | May 22, 2018 | — |
Building plan review Building Inspection · BLDG | May 23, 2018 | Jul 25, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jun 19, 2018 | Jun 20, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2018 | Jul 10, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jul 30, 2018 | Jul 31, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2018 | Aug 8, 2018 | — |
Zoning review Planning · CP-ZOC | Aug 8, 2018 | Aug 16, 2018 | — |
Permit Processing Center Building Inspection · PPC | Aug 16, 2018 | Aug 16, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2018 | May 17, 2019 | — |
Development fee collection Building Inspection · DFCU | Dec 5, 2018 | Dec 5, 2018 | — |
Addendum 1: Arch / structure / t-24 / final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 25, 2019 | Jun 25, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 25, 2019 | Aug 7, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 25, 2019 | Jan 9, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2019 | Jan 9, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2019 | May 5, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2019 | Sep 12, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2020 | May 14, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 18, 2020 | Oct 21, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2020 | Nov 13, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $495,000
| Name | Role | License on permit |
|---|---|---|
| Pak-Yat Lee Sedes Architecture | Architect | C-30921 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026