Scope of work
As written on the permit application.

To erect 3 stories, 1 basement, type v-b, single family residence.

Timeline
Key dates from the city record.
Filed
Aug 31, 2017
Issued
Jun 7, 2023 (69 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
57 stops across 6 departments
Comments issued
15 times, by Permit Center, Building Inspection, Fire Department, Public Works
Put on hold
4 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 31, 2017—

Zoning review

Planning · CP-ZOC

Oct 1, 2021—

Building plan review

Building Inspection · BLDG

Nov 21, 2022—

Fire prevention review

Fire Department · SFFD

Apr 17, 2023—

Street use and mapping

Public Works · DPW-BSM

Sep 2, 2022—

Urban forestry

Public Works · DPW-BUF

Nov 2, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Dec 12, 2022—

Street use and mapping

Public Works · DPW-BSM

Dec 13, 2022—

Fire prevention review

Fire Department · SFFD

Mar 28, 2023—

Fire prevention review

Fire Department · SFFD

Apr 13, 2023—

Building plan review

Building Inspection · BLDG

Apr 17, 2023—

Zoning review

Planning · CP-ZOC

Apr 25, 2023—

Zoning review

Planning · CP-ZOC

Apr 27, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 28, 2023—

Central Permit Bureau

Building Inspection · CPB

Jun 7, 2023—

Addendum 1: Final plans

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 30, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 26, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Apr 29, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 29, 2024Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Aug 19, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 14, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Aug 15, 2024Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Aug 19, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 20, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 16, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Sep 19, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 20, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Sep 23, 2024Administrative

Building plan review

Building Inspection · BLDG

Nov 5, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 4, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Oct 2, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 8, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 27, 2024Approved

Zoning review

Planning · CP-ZOC

Sep 24, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 3, 2025Administrative

Urban forestry

Public Works · DPW-BUF

Nov 5, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 15, 2025Administrative

Public Utilities Commission review

Public Utilities · SFPUC

Mar 3, 2025Approved

Fire prevention review

Fire Department · SFFD

Feb 26, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 27, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 6, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 26, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 28, 2025Approved

Building plan review

Building Inspection · BLDG

May 8, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

May 28, 2025Approved

Fire prevention review

Fire Department · SFFD

May 7, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 12, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jun 6, 2025Issued Comments

Zoning review

Planning · CP-ZOC

May 14, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jun 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 30, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 4, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 20, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 16, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 9, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jun 18, 2025Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Issued
Estimated cost
$573,200
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John Alan Goldman

Goldman Architects

ArchitectC14203
Jesus Francisco Sierra

Sierra Engineering Group

EngineerS3298
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201708316559 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record