1353 Stevenson St
San Francisco permit 201708316644 · Mission
Legalize 1 bedroom, 1 bathroom unit (unit 7) per ord 43-14; lower slab and add bicycleparking.
- Filed
- Aug 31, 2017
- Issued
- Feb 22, 2019 (18 months after filing)
- Completed
- Nov 14, 2019 (9 months after issuance)
- Review stops
- 12 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 1, 2017 | Sep 1, 2017 | — |
Zoning review Planning · CP-ZOC | Sep 1, 2017 | Nov 1, 2017 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2017 | Dec 13, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 15, 2017 | Nov 15, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 13, 2017 | Dec 13, 2017 | — |
Fire prevention review Fire Department · SFFD | Dec 13, 2017 | Dec 15, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2017 | Jan 16, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 21, 2017 | Jan 11, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 17, 2018 | Jan 24, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jan 17, 2018 | Jan 25, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2018 | Feb 7, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2018 | Feb 22, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $64,000
| Name | Role | License on permit |
|---|---|---|
| Claudio Martonffy Claudio Martonffy Design | Architect | 34835 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020