4408 03rd St
San Francisco permit 201709127786 · Bayview Hunters Point
To comply with soft story retrofit per sfbc ch 34-b fema p807 residential only
- Filed
- Sep 12, 2017
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 4 departments
- Comments issued
- None
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 12, 2017 | Sep 12, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2017 | Sep 12, 2017 | — |
Building plan review Building Inspection · BLDG | Sep 13, 2017 | Dec 10, 2019 | — |
Fire prevention review Fire Department · SFFD | Nov 1, 2017 | Dec 11, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2017 | Oct 11, 2018 | — |
Zoning review Planning · CP-ZOC | Feb 28, 2020 | Feb 28, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2020 | Jun 6, 2024 | — |
Fire prevention review Fire Department · SFFD | Mar 4, 2020 | Mar 6, 2020 | — |
Permit Processing Center Building Inspection · PPC | Mar 8, 2024 | In progress | In Progress |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2024 | Jun 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $80,000
| Name | Role | License on permit |
|---|---|---|
| Humza Shahid Chowdhry Hc Structural Engineering Inc. | Engineer | S-6091 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026