1415 Sanchez St
San Francisco permit 201709138010 · Noe Valley
Convert 1st flr storage to living space, merge 2nd & 3rd flr, relocate 1 unit to 1st flr inc (n) kitchen & bath. add attached garage at side alley & raise bldg to allow access. rear addition & deck. relocate & renovate kit @ 2nd flr, delete full bath & install 1/2 bath, 2 new baths @ 3rd flr.
- Filed
- Sep 13, 2017
- Issued
- May 20, 2019 (20 months after filing)
- Completed
- Dec 21, 2022 (43 months after issuance)
- Review stops
- 29 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 11 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 15, 2017 | Sep 15, 2017 | — |
Zoning review Planning · CP-ZOC | Sep 18, 2017 | Jan 28, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Oct 16, 2018 | Oct 29, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 29, 2019 | Feb 7, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 7, 2019 | Feb 11, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2019 | Mar 21, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 19, 2019 | Mar 13, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 4, 2019 | Mar 14, 2019 | — |
Development fee collection Building Inspection · DFCU | Mar 19, 2019 | Mar 19, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 22, 2019 | Mar 22, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2019 | May 20, 2019 | — |
Addendum 1: Structure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Street use and mapping Public Works · DPW-BSM | Jul 1, 2018 | Nov 5, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 21, 2019 | May 21, 2019 | — |
Building plan review Building Inspection · BLDG | May 21, 2019 | Oct 18, 2019 | — |
Permit Processing Center Building Inspection · PPC | Nov 7, 2019 | Nov 7, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2019 | Jan 6, 2020 | — |
Addendum 2: Arch,t-24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 21, 2019 | May 21, 2019 | — |
Building plan review Building Inspection · BLDG | May 21, 2019 | Jul 18, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2019 | Jul 18, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2019 | Jan 9, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2019 | Jul 3, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2019 | Feb 1, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2020 | Feb 5, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2020 | Feb 5, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2020 | Feb 13, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 13, 2020 | Feb 13, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2020 | Feb 13, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 14, 2020 | Feb 14, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2020 | Feb 24, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Eric Arnold | Engineer | C66537 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022