1415 Sanchez St

San Francisco permit 201709138010 · Noe Valley

AdditionFull plan reviewComplete
Street view · Feb 2022
Google Street View of 1415 Sanchez St, Feb 2022
Scope of work
As written on the permit application.

Convert 1st flr storage to living space, merge 2nd & 3rd flr, relocate 1 unit to 1st flr inc (n) kitchen & bath. add attached garage at side alley & raise bldg to allow access. rear addition & deck. relocate & renovate kit @ 2nd flr, delete full bath & install 1/2 bath, 2 new baths @ 3rd flr.

Timeline
Key dates from the city record.
Filed
Sep 13, 2017
Issued
May 20, 2019 (20 months after filing)
Completed
Dec 21, 2022 (43 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
11 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 15, 2017—

Zoning review

Planning · CP-ZOC

Jan 28, 2019—

Planning neighborhood notice

Planning · CP-NP

Oct 29, 2018—

Building plan review

Building Inspection · BLDG

Feb 7, 2019—

Building plan review

Building Inspection · BLDG

Feb 11, 2019—

Street use and mapping

Public Works · DPW-BSM

Mar 21, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 13, 2019—

Building plan review

Building Inspection · BLDG

Mar 14, 2019—

Development fee collection

Building Inspection · DFCU

Mar 19, 2019—

Permit Processing Center

Building Inspection · PPC

Mar 22, 2019—

Central Permit Bureau

Building Inspection · CPB

May 20, 2019—

Addendum 1: Structure

Review stopFinishedResult

Street use and mapping

Public Works · DPW-BSM

Nov 5, 2019—

Central Permit Bureau

Building Inspection · CPB

May 21, 2019—

Building plan review

Building Inspection · BLDG

Oct 18, 2019—

Permit Processing Center

Building Inspection · PPC

Nov 7, 2019—

Central Permit Bureau

Building Inspection · CPB

Jan 6, 2020—

Addendum 2: Arch,t-24,final plans

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 21, 2019—

Building plan review

Building Inspection · BLDG

Jul 18, 2019—

Mechanical and energy plan review

Building Inspection · MECH

Jul 18, 2019—

Street use and mapping

Public Works · DPW-BSM

Jan 9, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 3, 2019—

Building plan review

Building Inspection · BLDG

Feb 1, 2020—

Mechanical and energy plan review

Building Inspection · MECH

Feb 5, 2020—

Street use and mapping

Public Works · DPW-BSM

Feb 5, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 13, 2020—

Building plan review

Building Inspection · BLDG

Feb 13, 2020—

Structural plan approval

Building Inspection · PAD-STR

Feb 13, 2020—

Permit Processing Center

Building Inspection · PPC

Feb 14, 2020—

Central Permit Bureau

Building Inspection · CPB

Feb 24, 2020—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$650,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Andrew Eric ArnoldEngineerC66537
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201709138010 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record