2758 Filbert St
San Francisco permit 201710131247 · Marina
Renovation of an existing single family house. the new addition inlcludes one new story 3 additional beds and 2.5 baths and a rear year addition
- Filed
- Oct 13, 2017
- Issued
- Oct 16, 2019 (24 months after filing)
- Completed
- Dec 11, 2025 (74 months after issuance)
- Review stops
- 27 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 13, 2017 | Oct 13, 2017 | — |
Zoning review Planning · CP-ZOC | Oct 13, 2017 | Jun 13, 2019 | — |
Planning discretionary review Planning · CP-DR | Feb 11, 2019 | Feb 11, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jun 13, 2019 | Jun 13, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 14, 2019 | Jul 12, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 14, 2019 | Aug 28, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2019 | Jul 29, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 30, 2019 | Aug 23, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2019 | Sep 3, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2019 | Sep 5, 2019 | — |
Zoning review Planning · CP-ZOC | Sep 5, 2019 | Sep 11, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 11, 2019 | Sep 19, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2019 | Oct 16, 2019 | — |
Addendum 1: Foundation & superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 18, 2019 | Dec 18, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 18, 2019 | Feb 21, 2020 | — |
Building plan review Building Inspection · BLDG | Mar 6, 2020 | Aug 26, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2020 | Sep 2, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 3, 2020 | Sep 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2020 | Oct 27, 2020 | — |
Addendum 2: Architecture,electrical, mech engineering
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 18, 2019 | Dec 18, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 18, 2019 | Mar 5, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 14, 2020 | Mar 12, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 5, 2020 | Jun 10, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 5, 2020 | Mar 12, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2020 | May 28, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jun 11, 2020 | Jun 11, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jun 11, 2020 | Jun 19, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,330,000
| Name | Role | License on permit |
|---|---|---|
| John S Winder Winder Gibson Arch. | Architect | 13305 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2017