73 Eagle St
San Francisco permit 201710191761 · Castro/Upper Market
Remodel (e) garage to include laundry & utilities. add a 403 sq ft apartment. remodel front facade to include deck on 2nd story.
- Filed
- Oct 19, 2017
- Issued
- Jul 20, 2022 (57 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 4 departments
- Comments issued
- None
- Put on hold
- 9 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 31, 2017 | Oct 31, 2017 | — |
Zoning review Planning · CP-ZOC | Oct 31, 2017 | Sep 10, 2018 | — |
Planning neighborhood notice Planning · CP-NP | May 18, 2018 | Jun 25, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2018 | Oct 3, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 3, 2018 | Oct 18, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2018 | Aug 3, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Nov 2, 2018 | Nov 9, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2018 | Jan 30, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 18, 2020 | May 4, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2021 | Aug 30, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2021 | May 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 2, 2021 | Sep 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2022 | May 10, 2022 | — |
Zoning review Planning · CP-ZOC | May 10, 2022 | Jun 30, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 5, 2022 | Jul 7, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2022 | Jul 20, 2022 | — |
Addendum 1: Final - struct,arch,t24, mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 15, 2022 | Aug 15, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 15, 2022 | Jul 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2022 | Jul 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2022 | Dec 16, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 19, 2022 | Dec 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2023 | Aug 2, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 2, 2023 | Aug 7, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 7, 2023 | Aug 10, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2023 | Jul 5, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Tyler Gleeson Kobick Design Draw Build | Architect | C36432 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025