743 Vermont St
San Francisco permit 201710272504 · Potrero Hill
To comply w/ nov #201928061, demo rear portion of (e)house on 3rd fl and portions of 2nd fl. extension to rear (east) and north for addition of 136 sf to bldb footprint. relocation of interior stairway and remodel kitchen, master bedrm, baths, closet areas
- Filed
- Oct 27, 2017
- Issued
- Sep 26, 2020 (35 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 27, 2017 | Oct 27, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 27, 2017 | Oct 27, 2017 | — |
Zoning review Planning · CP-ZOC | Oct 27, 2017 | Feb 27, 2019 | — |
Planning discretionary review Planning · CP-DR | Nov 15, 2018 | Sep 1, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Jan 2, 2019 | Sep 1, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 28, 2019 | Mar 8, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 8, 2019 | Apr 11, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 12, 2019 | Feb 18, 2020 | — |
Zoning review Planning · CP-ZOC | May 21, 2019 | Feb 12, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 19, 2020 | Feb 20, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 19, 2020 | Feb 19, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 24, 2020 | Sep 8, 2020 | — |
Zoning review Planning · CP-ZOC | Mar 4, 2020 | Sep 1, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2020 | Sep 4, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 8, 2020 | Sep 26, 2020 | — |
Addendum 1: Arch, stru, mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 30, 2021 | Mar 30, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2021 | Jul 22, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 22, 2021 | Aug 16, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 16, 2021 | Aug 18, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 19, 2021 | Aug 23, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 25, 2021 | Aug 25, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2021 | Sep 13, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $240,000
| Name | Role | License on permit |
|---|---|---|
| William Geoffrey Walters Disseny | Architect | C20271 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2014