33 New Montgomery St
San Francisco permit 201710302567 · Financial District/South Beach
Replacement of existing atm's with atm's. minor electrical, structural. change one office & one atm room to a training room. n/a maher ordinance
- Filed
- Oct 30, 2017
- Issued
- Jan 21, 2022 (51 months after filing)
- Completed
- Jan 11, 2023 (12 months after issuance)
- Review stops
- 14 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 30, 2017 | Oct 30, 2017 | — |
Fire prevention review Fire Department · SFFD | Apr 5, 2018 | Apr 5, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Apr 13, 2018 | Apr 13, 2018 | — |
Zoning review Planning · CP-ZOC | Apr 13, 2018 | Feb 10, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2021 | Jul 30, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2021 | Nov 18, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Jun 11, 2021 | Oct 22, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 21, 2021 | Nov 2, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 30, 2021 | Aug 2, 2021 | — |
Fire prevention review Fire Department · SFFD | Oct 22, 2021 | Nov 1, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 19, 2021 | Nov 30, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 1, 2021 | Dec 7, 2021 | — |
Permit Processing Center Building Inspection · PPC | Dec 7, 2021 | Dec 21, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 21, 2021 | Jan 21, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $175,000
| Name | Role | License on permit |
|---|---|---|
| Michael Rane Downey Gensler Architect | Architect | C19329 |
| Blake Dilsworth | Engineer | 3929 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025