1270 Church St
San Francisco permit 201711022974 · Noe Valley
Add (2) additional dwelling units on the ground floor per ordinance 162-16. sprinklers deferred.
- Filed
- Nov 2, 2017
- Issued
- Oct 19, 2018 (12 months after filing)
- Completed
- Jul 31, 2019 (9 months after issuance)
- Review stops
- 21 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 6, 2017 | Nov 6, 2017 | — |
Zoning review Planning · CP-ZOC | Nov 6, 2017 | Apr 16, 2018 | — |
Building plan review Building Inspection · BLDG | Apr 17, 2018 | Apr 23, 2018 | — |
Fire prevention review Fire Department · SFFD | Apr 23, 2018 | Sep 14, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2018 | Jun 6, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 7, 2018 | Jun 23, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 30, 2018 | Sep 4, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 14, 2018 | Sep 19, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2018 | Sep 25, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2018 | Sep 28, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 28, 2018 | Oct 3, 2018 | — |
Permit Processing Center Building Inspection · PPC | Oct 5, 2018 | Oct 5, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2018 | Oct 19, 2018 | — |
Addendum 1: Superstructure,t24,arch,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 13, 2018 | Dec 13, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 13, 2018 | Dec 18, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 18, 2018 | Dec 20, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2018 | Dec 20, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2018 | Jan 7, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 24, 2018 | Jan 3, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jan 8, 2019 | Jan 8, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2019 | Jan 31, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| Janet Coral Campbell Campbell & Associates | Architect | C18808 |
| Donna Leigh Schumacher Donna Schumacher Arch. | Architect | C23503 |
| Narasimha D Prasanth Tanikella Zenith Engineers | Engineer | C81660 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021