646 03rd Av
San Francisco permit 201711063149 · Inner Richmond
Horizontal addition @ rear yard of 1-fam dwelling. addition includes excavation at lvl 1 to create a family rm, new bath, laundry & rear yard patio. a new interior stair connects 1st & 2nd lvls. lvl 2 includes a remodeled kitchen & powder rm, new deck & interior stairs to rear yard. lvl 3 includes a
- Filed
- Nov 6, 2017
- Issued
- Dec 19, 2018 (13 months after filing)
- Completed
- Sep 1, 2020 (20 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 6, 2017 | Nov 6, 2017 | — |
Zoning review Planning · CP-ZOC | Nov 6, 2017 | May 18, 2018 | — |
Planning neighborhood notice Planning · CP-NP | May 18, 2018 | May 18, 2018 | — |
Building plan review Building Inspection · BLDG | May 21, 2018 | Sep 27, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2018 | Jul 5, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2018 | Jul 20, 2018 | — |
Zoning review Planning · CP-ZOC | Oct 31, 2018 | Nov 1, 2018 | — |
Development fee collection Building Inspection · DFCU | Nov 2, 2018 | Nov 2, 2018 | — |
Permit Processing Center Building Inspection · PPC | Nov 2, 2018 | Nov 2, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2018 | Dec 19, 2018 | — |
Addendum 1: Arch / mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 21, 2018 | Dec 21, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2018 | Feb 20, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2019 | Feb 7, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2019 | Feb 26, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 26, 2019 | Mar 15, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2019 | Mar 14, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2019 | Apr 11, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 11, 2019 | Apr 16, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2019 | Apr 24, 2019 | — |
Addendum 2: Foundation,structure,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 1, 2019 | Feb 1, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2019 | Mar 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2019 | Mar 29, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 1, 2019 | Apr 1, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2019 | Apr 4, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $626,044
| Name | Role | License on permit |
|---|---|---|
| Heather Rae Hart Samaha & Hart Architecture | Architect | C31257 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020