139 A Sweeny St
San Francisco permit 201711133870 · Portola
Add one adu at 1st flr per ord no 162-16 under this permit. second unit legalized under app #2017-1113-3867.
- Filed
- Nov 13, 2017
- Issued
- Dec 19, 2022 (61 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 5, 2017 | Dec 5, 2017 | — |
Zoning review Planning · CP-ZOC | Dec 5, 2017 | Jun 9, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Oct 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2021 | Nov 4, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 2, 2021 | Nov 2, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2021 | Jul 22, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 17, 2021 | Sep 17, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 4, 2022 | Nov 7, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 9, 2022 | Dec 9, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 12, 2022 | Dec 12, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2022 | Dec 19, 2022 | — |
Addendum 1: Arch / structural / t-24, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2023 | Mar 7, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2023 | Aug 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2023 | Jul 31, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 2, 2023 | May 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2023 | May 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2023 | Jul 31, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2023 | Aug 9, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 9, 2023 | Aug 10, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2023 | Aug 23, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 25, 2023 | Aug 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 1, 2023 | Sep 5, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 5, 2023 | Sep 15, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2023 | Sep 19, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $30,000
| Name | Role | License on permit |
|---|---|---|
| Pak-Yat Lee Sedes Architecture | Architect | C30921 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026