2265 Beach St
San Francisco permit 201711295058 · Marina
Remove boiler room at rear of building, add accessory dwelling unit at rear of garage per ordinance 162-16. soft story permit #2017-0426-4957 for reference.
- Filed
- Nov 29, 2017
- Issued
- Jun 19, 2018 (7 months after filing)
- Completed
- Jun 7, 2021 (36 months after issuance)
- Review stops
- 21 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2017 | Nov 30, 2017 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2017 | Feb 26, 2018 | — |
Building plan review Building Inspection · BLDG | Feb 27, 2018 | Mar 20, 2018 | — |
Fire prevention review Fire Department · SFFD | Mar 20, 2018 | Mar 22, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2018 | Mar 27, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 28, 2018 | Apr 4, 2018 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2018 | Jun 14, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 15, 2018 | Jun 18, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jun 15, 2018 | Jun 18, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2018 | Jun 19, 2018 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 19, 2018 | Jun 19, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 19, 2018 | Jun 26, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 22, 2018 | Jun 22, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2018 | Jun 26, 2018 | — |
Fire prevention review Fire Department · SFFD | Jun 26, 2018 | Aug 14, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jul 2, 2018 | Jul 5, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2018 | Jul 12, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 15, 2018 | Aug 20, 2018 | — |
Fire prevention review Fire Department · SFFD | Aug 15, 2018 | Aug 15, 2018 | — |
Permit Processing Center Building Inspection · PPC | Aug 21, 2018 | Aug 21, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 21, 2018 | Aug 21, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $126,000
| Name | Role | License on permit |
|---|---|---|
| David R Teeters | Architect | C011720 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025