856 Capp St
San Francisco permit 201712065684 · Mission
Horizontal addtion & create new 9 units residential low-rise. retain (e) institutional structure.
- Filed
- Dec 6, 2017
- Issued
- May 31, 2019 (18 months after filing)
- Completed
- Apr 19, 2021 (23 months after issuance)
- Review stops
- 33 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 9 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Dec 6, 2017 | Dec 6, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2017 | Dec 6, 2017 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2017 | Mar 1, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jan 10, 2019 | Feb 21, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 4, 2019 | May 6, 2019 | — |
Fire prevention review Fire Department · SFFD | Apr 1, 2019 | May 6, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 4, 2019 | Apr 5, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2019 | May 20, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 16, 2019 | May 16, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2019 | May 29, 2019 | — |
Development fee collection Building Inspection · DFCU | May 29, 2019 | May 29, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 29, 2019 | May 29, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 29, 2019 | May 31, 2019 | — |
Addendum 1: Foundation.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 7, 2019 | Jun 7, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 7, 2019 | Jun 24, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jun 24, 2019 | Jun 25, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jun 26, 2019 | Jun 26, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2019 | Jun 26, 2019 | — |
Addendum 2: Superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 21, 2019 | Jun 21, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2019 | Jul 31, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2019 | Sep 20, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2019 | Aug 28, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 20, 2019 | Sep 20, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2019 | Sep 20, 2019 | — |
Addendum 3: Architectural & mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 24, 2019 | Jun 24, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 24, 2019 | Sep 19, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 23, 2019 | Dec 30, 2019 | — |
Fire prevention review Fire Department · SFFD | Oct 21, 2019 | Dec 18, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2019 | Oct 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2019 | Oct 24, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 30, 2019 | Feb 21, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 30, 2019 | Feb 21, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 21, 2020 | Feb 24, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,545,000
| Name | Role | License on permit |
|---|---|---|
| Andrew J Davis Fluid Studios | Architect | C28439 |
| David W Kane Harrell Kane S.E. Inc. | Engineer | S-5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026