CheckMyDesigner

2750 19th St

San Francisco permit 201712156665 · Mission

Commercial or tenant improvement (type unconfirmed)Full plan reviewComplete
Street view · Feb 2014
Google Street View of 2750 19th St, Feb 2014
Scope of work
As written on the permit application.

Entire removal of (e) wood frame structure with retention of brick facade, 6 story addition including new subterranean parking, new ground floor commercial & 63 new residential units. (r-2,m,a-2,a-3,s-2) ** maher: n/a **

Timeline
Key dates from the city record.
Filed
Dec 15, 2017
Issued
Apr 15, 2020 (28 months after filing)
Completed
Jan 15, 2026 (69 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
80 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
26 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 15, 2017—

Zoning review

Planning · CP-ZOC

Sep 23, 2019—

Building plan review

Building Inspection · BLDG

Jan 22, 2020—

Fire prevention review

Fire Department · SFFD

Jan 21, 2020—

Street use and mapping

Public Works · DPW-BSM

Jan 29, 2020—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 15, 2020—

Development fee collection

Building Inspection · DFCU

Jan 31, 2020—

Permit Processing Center

Building Inspection · PPC

Feb 4, 2020—

Central Permit Bureau

Building Inspection · CPB

Apr 15, 2020—

Addendum 1: Foundation / superstructure.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2020—

Building plan review

Building Inspection · BLDG

Jun 18, 2021—

Street use and mapping

Public Works · DPW-BSM

Jul 2, 2021—

Public health review

Public Health · HEALTH

Jul 6, 2021—

Permit Processing Center

Building Inspection · PPC

Jul 6, 2021—

Central Permit Bureau

Building Inspection · CPB

Jul 21, 2021—

Addendum 2: Architectural / mep.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2020—

Building plan review

Building Inspection · BLDG

Dec 1, 2021—

Mechanical and energy plan review

Building Inspection · MECH

Feb 2, 2022—

Fire prevention review

Fire Department · SFFD

Jun 22, 2022—

Electrical plan review

Building Inspection · MECH-E

Jun 13, 2022—

Street use and mapping

Public Works · DPW-BSM

Feb 3, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 29, 2021—

Zoning review

Planning · CP-ZOC

Sep 7, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jun 7, 2022—

Zoning review

Planning · CP-ZOC

Sep 7, 2022—

Permit Processing Center

Building Inspection · PPC

Sep 23, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 15, 2022—

Central Permit Bureau

Building Inspection · CPB

Sep 30, 2022—

Addendum 3: Fire sprinkler.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 15, 2022—

Fire prevention review

Fire Department · SFFD

Jul 27, 2022—

Permit Processing Center

Building Inspection · PPC

Jul 28, 2022—

Central Permit Bureau

Building Inspection · CPB

Aug 4, 2022—

Addendum 4: Metal stairs.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 7, 2022—

Building plan review

Building Inspection · BLDG

Apr 26, 2022—

Fire prevention review

Fire Department · SFFD

Oct 6, 2022—

Permit Processing Center

Building Inspection · PPC

Oct 6, 2022—

Central Permit Bureau

Building Inspection · CPB

Oct 13, 2022—

Addendum 5: Stormwater.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 24, 2021—

Permit Processing Center

Building Inspection · PPC

Oct 22, 2021—

Plumbing plan check

Building Inspection · PID-PC

Jun 17, 2021—

Central Permit Bureau

Building Inspection · CPB

Nov 3, 2021—

Addendum 6: Fire alarm system, elevator landing & 2-way communication system.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 20, 2022—

Fire prevention review

Fire Department · SFFD

Jan 30, 2023—

Permit Processing Center

Building Inspection · PPC

Jan 31, 2023—

Central Permit Bureau

Building Inspection · CPB

Feb 2, 2023—

Addendum 7: Errcs.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 24, 2022—

Fire prevention review

Fire Department · SFFD

Sep 14, 2022—

Permit Processing Center

Building Inspection · PPC

Sep 15, 2022—

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2022—

Addendum 8: Exterior building maintenance.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 24, 2022—

Building plan review

Building Inspection · BLDG

Nov 29, 2022—

Fire prevention review

Fire Department · SFFD

Oct 27, 2022—

Street use and mapping

Public Works · DPW-BSM

Dec 1, 2022—

Permit Processing Center

Building Inspection · PPC

Dec 2, 2022—

Central Permit Bureau

Building Inspection · CPB

Dec 8, 2022—

Addendum 9: Exterior metal framing

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 1, 2022—

Building plan review

Building Inspection · BLDG

Mar 6, 2023—

Fire prevention review

Fire Department · SFFD

Mar 8, 2023—

Building plan review

Building Inspection · BLDG

Mar 6, 2023—

Permit Processing Center

Building Inspection · PPC

Mar 9, 2023—

Central Permit Bureau

Building Inspection · CPB

Mar 14, 2023—

Addendum 10: Evacuation signage

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2023—

Fire prevention review

Fire Department · SFFD

Jun 19, 2023—

Fire prevention review

Fire Department · SFFD

Jul 19, 2023—

Permit Processing Center

Building Inspection · PPC

Jul 19, 2023—

Central Permit Bureau

Building Inspection · CPB

Jul 21, 2023—

Addendum 11: Health

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 23, 2023—

Building plan review

Building Inspection · BLDG

Mar 9, 2023—

Public health review

Public Health · HEALTH

Mar 27, 2023—

Permit Processing Center

Building Inspection · PPC

Mar 28, 2023—

Central Permit Bureau

Building Inspection · CPB

Mar 30, 2023—

Addendum 12: Elevator penthouse details

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 9, 2022—

Building plan review

Building Inspection · BLDG

Mar 7, 2023—

Zoning review

Planning · CP-ZOC

Jan 19, 2023—

Fire prevention review

Fire Department · SFFD

Jan 24, 2023—

Building plan review

Building Inspection · BLDG

Jan 24, 2023—

Fire prevention review

Fire Department · SFFD

Feb 9, 2023—

Zoning review

Planning · CP-ZOC

Mar 2, 2023—

Permit Processing Center

Building Inspection · PPC

Mar 7, 2023—

Central Permit Bureau

Building Inspection · CPB

Mar 14, 2023—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$28,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Steven Perry

Perry Architectus, Inc.

ArchitectC26289
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201712156665 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record