719 Faxon Av
San Francisco permit 201712206995 · West of Twin Peaks
Two-story 644 sf addition, new stair, kitchen & bath remodel.
- Filed
- Dec 20, 2017
- Issued
- Sep 21, 2018 (9 months after filing)
- Completed
- Jan 29, 2021 (28 months after issuance)
- Review stops
- 19 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2017 | Dec 20, 2017 | — |
Zoning review Planning · CP-ZOC | Dec 20, 2017 | Aug 2, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Apr 19, 2018 | Aug 2, 2018 | — |
Planning discretionary review Planning · CP-DR | Jun 4, 2018 | Aug 2, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 7, 2018 | Aug 10, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2018 | Aug 13, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2018 | Sep 15, 2018 | — |
Permit Processing Center Building Inspection · PPC | Sep 17, 2018 | Sep 17, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2018 | Sep 21, 2018 | — |
Addendum 1: Foundation,struct,t24,arch,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2018 | Sep 21, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2018 | Sep 28, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 28, 2018 | Oct 1, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 28, 2018 | Oct 9, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2018 | Oct 23, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2018 | Oct 11, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 25, 2018 | Nov 21, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 21, 2018 | Dec 4, 2018 | — |
Permit Processing Center Building Inspection · PPC | Dec 4, 2018 | Dec 4, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2018 | Dec 7, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $175,000
| Name | Role | License on permit |
|---|---|---|
| Brandon D Marshall Fog Studio | Architect | C33665 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025