125 Alpine Tr
San Francisco permit 201712217149 · Castro/Upper Market
Vertical addition of new meditation room south of (e) house above the (e) garage structure.
- Filed
- Dec 21, 2017
- Issued
- Jun 14, 2019 (18 months after filing)
- Completed
- May 22, 2023 (47 months after issuance)
- Review stops
- 20 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 21, 2017 | Dec 21, 2017 | — |
Zoning review Planning · CP-ZOC | Dec 21, 2017 | Jan 31, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Dec 12, 2018 | Jan 23, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 31, 2019 | Feb 11, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2019 | Feb 12, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 21, 2019 | Feb 21, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 21, 2019 | Feb 25, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2019 | Mar 26, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 27, 2019 | Mar 27, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2019 | Jun 14, 2019 | — |
Addendum 1: Struct,t-24,arch,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 14, 2019 | Jun 14, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 14, 2019 | Nov 19, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2019 | Jan 10, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2019 | Nov 8, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2019 | Nov 8, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 10, 2020 | Jan 16, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 16, 2020 | Jan 17, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2020 | Jan 27, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 27, 2020 | Jan 27, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 27, 2020 | Jul 11, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $43,440
| Name | Role | License on permit |
|---|---|---|
| Emily R Huang Huang Iboshi Architecture | Architect | C26901 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025