246 Faxon Av
San Francisco permit 201712227291 · Oceanview/Merced/Ingleside
Replace/reconfigure (e) family room. add interior stair, add solar, remodel kitchen, garage t0 1-hr protection, add bedroom, bathroom & media room @ 1st fl garden level
- Filed
- Dec 22, 2017
- Issued
- Sep 15, 2021 (45 months after filing)
- Completed
- May 6, 2024 (32 months after issuance)
- Review stops
- 21 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 11, 2018 | Jan 11, 2018 | — |
Zoning review Planning · CP-ZOC | Jan 11, 2018 | Mar 19, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jan 23, 2019 | Mar 5, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 20, 2019 | Sep 6, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 18, 2019 | May 25, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2019 | May 16, 2019 | — |
Zoning review Planning · CP-ZOC | May 26, 2021 | Jun 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2021 | Jun 30, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jul 2, 2021 | Jul 2, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2021 | Sep 15, 2021 | — |
Addendum 1: Title 24, struct, foundation, arch
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 14, 2022 | Feb 14, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 14, 2022 | Jun 13, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2022 | Jun 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 10, 2022 | Jun 13, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 13, 2022 | Jul 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2022 | Jul 13, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2022 | Jul 21, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2022 | Jul 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2022 | Jul 26, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 28, 2022 | Aug 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2022 | Nov 10, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Andy Forrest Andy Forest P.E. | Engineer | C29620 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2015