2637 Union St
San Francisco permit 201801088000 · Marina
Increase entry lvl height by raising ground lvl wall by 1'-0"; convert entry lvl suite to 2nd dwelling unit; replace (e) window @ entry lvl w/ roll up door to accomodate off street parking; horizontal addition in the rear yard; setback vertical addition above (e) 2nd lvl.
- Filed
- Jan 8, 2018
- Issued
- Jul 23, 2026 (102 months after filing)
- Completed
- Not completed yet
- Review stops
- 44 stops across 6 departments
- Comments issued
- 9 times, by Public Utilities, Permit Center, Building Inspection, Fire Department
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 10, 2018 | Jan 10, 2018 | — |
Zoning review Planning · CP-ZOC | Jan 10, 2018 | Aug 7, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Mar 13, 2020 | Aug 7, 2020 | Approved |
Planning neighborhood notice Planning · CP-NP | Apr 22, 2020 | Aug 7, 2020 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2020 | Nov 3, 2023 | Denied |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2020 | Sep 2, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2020 | Nov 15, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 12, 2024 | Mar 11, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jun 17, 2025 | Jul 2, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 7, 2025 | Jul 15, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 24, 2025 | Aug 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2025 | Aug 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 11, 2025 | Sep 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 11, 2025 | Aug 28, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 11, 2025 | Aug 22, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2025 | Aug 12, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Aug 11, 2025 | Aug 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2025 | Aug 13, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2025 | Aug 14, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 11, 2025 | Mar 11, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2025 | Aug 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 29, 2025 | Oct 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 29, 2025 | Nov 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 29, 2025 | Nov 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 29, 2025 | Oct 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2025 | Oct 30, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 29, 2025 | Nov 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 6, 2026 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2026 | Jan 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 6, 2026 | Jan 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 6, 2026 | Jan 20, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2026 | Jan 8, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2026 | Jan 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2026 | Feb 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2026 | Feb 6, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 2, 2026 | Feb 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2026 | Feb 3, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 4, 2026 | Feb 12, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 13, 2026 | Mar 11, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 17, 2026 | Feb 20, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 17, 2026 | Mar 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2026 | Jul 23, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,012,058
| Name | Role | License on permit |
|---|---|---|
| Maurice Lombardo Taylor Lombardo Architects | Architect | C26362 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2008