1839 26th Av
San Francisco permit 201801199067 · Sunset/Parkside
Horizontal rear addition which includes a remodeled kitchen ,roof, windows,finishes and fixtures throughout. 1 master bedroom, 1 bedroom,2 baths. life safety under seperate permit.
- Filed
- Jan 19, 2018
- Issued
- Nov 15, 2019 (22 months after filing)
- Completed
- Feb 2, 2023 (39 months after issuance)
- Review stops
- 19 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 19, 2018 | Jan 19, 2018 | — |
Zoning review Planning · CP-ZOC | Jan 19, 2018 | May 31, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Mar 11, 2019 | Apr 5, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 3, 2019 | Jun 20, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 20, 2019 | Jul 8, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jul 8, 2019 | Jul 9, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2019 | Jul 22, 2019 | — |
Development fee collection Building Inspection · DFCU | Jul 23, 2019 | Jul 23, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jul 23, 2019 | Jul 24, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2019 | Nov 15, 2019 | — |
Addendum 1: Foundation, superstructure, title 24, final plans.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2019 | Dec 20, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2019 | Apr 13, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2019 | Aug 26, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2020 | Aug 31, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | May 11, 2020 | Sep 1, 2020 | — |
Street use and mapping Public Works · DPW-BSM | May 14, 2020 | Apr 19, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 18, 2020 | May 22, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 26, 2020 | Apr 20, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Apr 20, 2021 | Apr 29, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $329,000
| Name | Role | License on permit |
|---|---|---|
| Sarah Louie Roitman Alan Zee Sarah-Louie Arch | Architect | C-33436 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025