61 Pleasant St
San Francisco permit 201801269697 · Nob Hill
Vertical addition of 1-story over (e) garage into a (1) bedroom, (1) bathroom unit. remodel of (e) garage. new design-build fire sprinkler system per nfpa-13r under separate permit.
- Filed
- Jan 26, 2018
- Issued
- Sep 15, 2021 (44 months after filing)
- Completed
- Not completed yet
- Review stops
- 27 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 26, 2018 | Jan 26, 2018 | — |
Zoning review Planning · CP-ZOC | Jan 26, 2018 | Sep 4, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Jan 21, 2020 | Jan 21, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2020 | Jan 11, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2020 | May 12, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2021 | Jul 14, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2021 | Apr 20, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 16, 2021 | Jul 20, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 21, 2021 | Aug 19, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 23, 2021 | Aug 23, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 24, 2021 | Aug 24, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2021 | Sep 15, 2021 | — |
Addendum 1: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 22, 2021 | Oct 22, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 22, 2021 | Apr 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2022 | Jun 29, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 17, 2022 | Jun 17, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 1, 2022 | Jul 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2022 | Jul 17, 2023 | — |
Addendum 2: Architectural,mech,electrical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 22, 2021 | Oct 22, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 22, 2021 | Jun 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 1, 2021 | May 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 29, 2021 | Jun 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2021 | Jun 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 4, 2022 | Jan 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 30, 2022 | Jul 1, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 5, 2022 | Jul 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 5, 2022 | Jul 17, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $89,195
| Name | Role | License on permit |
|---|---|---|
| John S Winder Winder Gibson Architects | Architect | C13305 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026