72 05th Av
San Francisco permit 201802131158 · Inner Richmond
Garage: rear horizontal addition @ existing garage/studio including new studio bath.
- Filed
- Feb 13, 2018
- Issued
- Jan 14, 2019 (11 months after filing)
- Completed
- Mar 30, 2021 (26 months after issuance)
- Review stops
- 23 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 13, 2018 | Feb 13, 2018 | — |
Zoning review Planning · CP-ZOC | Feb 13, 2018 | Oct 22, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 23, 2018 | Dec 4, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Nov 26, 2018 | Nov 29, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 30, 2018 | Dec 6, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2018 | Dec 10, 2018 | — |
Permit Processing Center Building Inspection · PPC | Dec 11, 2018 | Dec 11, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Dec 11, 2018 | Jan 14, 2019 | — |
Addendum 1: Structural foundation grades for the main house & garage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 22, 2019 | Jan 22, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 22, 2019 | Feb 22, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2019 | Feb 22, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2019 | Mar 6, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2019 | Mar 7, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2019 | May 28, 2019 | — |
Addendum 2: Arch/struct/mep/t24 for the main house & garage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 22, 2019 | Jan 22, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 22, 2019 | Mar 1, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2019 | Jun 14, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 19, 2019 | Feb 19, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 24, 2019 | May 29, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2019 | Jun 4, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 14, 2019 | Jun 27, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jun 27, 2019 | Jun 27, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2019 | Jul 23, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| Jonathan H Feldman Feldman Architecture | Architect | C28459 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2014