522 A Oak St
San Francisco permit 201802131174 · Hayes Valley
Legalization of existing dwelling unit to comply with nov #201708871 (eid) and 201798238(bid) per ord# 43-14.
- Filed
- Feb 13, 2018
- Issued
- Jan 14, 2019 (11 months after filing)
- Completed
- Jan 14, 2021 (24 months after issuance)
- Review stops
- 12 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Electrical inspector Building Inspection · EID-INSP | Dec 21, 2017 | Dec 21, 2017 | — |
Code enforcement Building Inspection · CES | Dec 21, 2017 | Dec 21, 2017 | — |
Building inspector Building Inspection · BID-INSP | Feb 13, 2018 | Feb 13, 2018 | — |
Intake Building Inspection · INTAKE | Feb 13, 2018 | Feb 13, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2018 | Feb 13, 2018 | — |
Zoning review Planning · CP-ZOC | Feb 13, 2018 | May 21, 2018 | — |
Building plan review Building Inspection · BLDG | May 22, 2018 | Aug 8, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2018 | Aug 8, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2018 | Aug 9, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2018 | Sep 13, 2018 | — |
Permit Processing Center Building Inspection · PPC | Sep 14, 2018 | Sep 14, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2018 | Jan 14, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $114,431
| Name | Role | License on permit |
|---|---|---|
| Garry L Baker Glb Architects | Architect | C6343 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025