2835 Octavia St
San Francisco permit 201802262270 · Marina
Horizontal addition and interior remodel of an (e) bldg containing 3 dwelling units. addition consists of expanding the bldg towards the rear yard by 3'-6"+ adding allowed rear yard 12'-0" one story obstruction.
- Filed
- Feb 26, 2018
- Issued
- Apr 23, 2021 (38 months after filing)
- Completed
- Not completed yet
- Review stops
- 28 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2018 | Mar 7, 2018 | — |
Zoning review Planning · CP-ZOC | Mar 7, 2018 | Apr 13, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Feb 25, 2020 | Jul 30, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 5, 2020 | Dec 29, 2020 | — |
Fire prevention review Fire Department · SFFD | Oct 7, 2020 | Jan 26, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2020 | Dec 4, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 7, 2020 | Feb 3, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 3, 2021 | Mar 17, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 18, 2021 | Mar 26, 2021 | — |
Fire prevention review Fire Department · SFFD | Mar 26, 2021 | Mar 30, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 6, 2021 | Apr 7, 2021 | — |
Permit Processing Center Building Inspection · PPC | Apr 8, 2021 | Apr 15, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2021 | Apr 23, 2021 | — |
Development fee collection Building Inspection · DFCU | Apr 22, 2021 | Apr 22, 2021 | — |
Addendum 1: Archtectural, t-24, structural, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 2, 2021 | Jul 2, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 2, 2021 | Mar 10, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 18, 2021 | Aug 24, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 16, 2021 | Mar 14, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 11, 2022 | Mar 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2022 | Apr 5, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 14, 2022 | Mar 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2022 | Mar 15, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 6, 2022 | Apr 18, 2022 | — |
Code enforcement Building Inspection · CES | Apr 19, 2022 | Apr 19, 2022 | — |
Building inspector Building Inspection · BID-INSP | Apr 19, 2022 | Apr 29, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 29, 2022 | May 4, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 29, 2022 | May 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 4, 2022 | May 9, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $703,443
| Name | Role | License on permit |
|---|---|---|
| Leonardo L Zylberberg Lz Architect | Architect | C27342 |
| Nilgun Asci Wolpe N. Y Engineering | Engineer | 68482 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026