2955 Pierce St
San Francisco permit 201803295043 · Marina
Connect (e) roof decks, new exterior finishes & lighting.
- Filed
- Mar 29, 2018
- Issued
- May 2, 2019 (13 months after filing)
- Completed
- Apr 30, 2020 (12 months after issuance)
- Review stops
- 19 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Electrical inspector Building Inspection · EID-INSP | Mar 29, 2018 | Mar 29, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2018 | Apr 2, 2018 | — |
Zoning review Planning · CP-ZOC | Apr 2, 2018 | Mar 19, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jul 2, 2018 | Mar 19, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 20, 2019 | Mar 22, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 22, 2019 | Apr 8, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 8, 2019 | Apr 11, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 11, 2019 | Apr 11, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 11, 2019 | Apr 12, 2019 | — |
Zoning review Planning · CP-ZOC | Apr 15, 2019 | Apr 18, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 19, 2019 | Apr 19, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 19, 2019 | May 2, 2019 | — |
Addendum 1: Struct,arch,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 8, 2019 | May 8, 2019 | — |
Building plan review Building Inspection · BLDG | May 8, 2019 | May 9, 2019 | — |
Building plan review Building Inspection · BLDG | May 9, 2019 | May 13, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | May 13, 2019 | May 13, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 13, 2019 | May 14, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2019 | May 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 15, 2019 | May 28, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $55,000
| Name | Role | License on permit |
|---|---|---|
| Andrew J Dunbar Interstice Architects | Architect | C28143 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025