CheckMyDesigner

709 Lyon St

San Francisco permit 201804237037 · Lone Mountain/USF

New buildingFull plan reviewComplete
Street view · Jun 2022
Google Street View of 709 Lyon St, Jun 2022
Scope of work
As written on the permit application.

To erect 4 stories, 1 basement, type iii-a, 5 unit residential bldg. arch/mep/sprinkler/standpipe/alarm deferred.

Timeline
Key dates from the city record.
Filed
Apr 23, 2018
Issued
Oct 24, 2019 (18 months after filing)
Completed
Dec 1, 2022 (37 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
34 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
12 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 23, 2018—

Zoning review

Planning · CP-ZOC

May 13, 2019—

Planning neighborhood notice

Planning · CP-NP

May 13, 2019—

Zoning review

Planning · CP-ZOC

May 13, 2019—

Building plan review

Building Inspection · BLDG

Jul 25, 2019—

Fire prevention review

Fire Department · SFFD

Jul 19, 2019—

Street use and mapping

Public Works · DPW-BSM

Jun 27, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 11, 2019—

Fire prevention review

Fire Department · SFFD

Aug 14, 2019—

Zoning review

Planning · CP-ZOC

Sep 11, 2019—

Permit Processing Center

Building Inspection · PPC

Sep 12, 2019—

Central Permit Bureau

Building Inspection · CPB

Oct 24, 2019—

Development fee collection

Building Inspection · DFCU

Sep 19, 2019—

Addendum 1: Foundation

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 24, 2019—

Building plan review

Building Inspection · BLDG

Jan 30, 2020—

Street use and mapping

Public Works · DPW-BSM

Feb 24, 2020—

Permit Processing Center

Building Inspection · PPC

Feb 24, 2020—

Central Permit Bureau

Building Inspection · CPB

Apr 17, 2020—

Addendum 2: Superstructure

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 18, 2020—

Building plan review

Building Inspection · BLDG

Nov 4, 2020—

Permit Processing Center

Building Inspection · PPC

Nov 9, 2020—

Central Permit Bureau

Building Inspection · CPB

Nov 14, 2020—

Addendum 3: Architectural & mep

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 20, 2020—

Building plan review

Building Inspection · BLDG

Jan 22, 2021—

Central Permit Bureau

Building Inspection · CPB

Dec 9, 2020—

Mechanical and energy plan review

Building Inspection · MECH

Feb 4, 2021—

Fire prevention review

Fire Department · SFFD

Feb 17, 2021—

Street use and mapping

Public Works · DPW-BSM

Jan 29, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 5, 2021—

Zoning review

Planning · CP-ZOC

Feb 26, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 3, 2021—

Fire prevention review

Fire Department · SFFD

Mar 8, 2021—

Permit Processing Center

Building Inspection · PPC

Mar 8, 2021—

Central Permit Bureau

Building Inspection · CPB

Mar 15, 2021—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Complete
Estimated cost
$3,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Zachary Joseph Maddry

Dmarc Studio

ArchitectC30718
Sarah Louie Roitman

Sarah Louie Roitman, Arch

ArchitectC33436
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201804237037 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record