4236 25th St

San Francisco permit 201805028044 · Noe Valley

ADUFull plan reviewFiled
Street view · Apr 2019
Google Street View of 4236 25th St, Apr 2019
Scope of work
As written on the permit application.

Existing unocuppied space at the ground level shall be converted to an accessory dwelling unit per add units ordinance no. 162-16.

Timeline
Key dates from the city record.
Filed
May 2, 2018
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 5 departments
Comments issued
5 times, by Building Inspection, Public Utilities
Put on hold
7 times
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

May 2, 2018—

Central Permit Bureau

Building Inspection · CPB

May 11, 2018—

Zoning review

Planning · CP-ZOC

Jun 10, 2020—

Permit Processing Center

Building Inspection · PPC

In progress—

Mechanical and energy plan review

Building Inspection · MECH

Jan 22, 2019—

Street use and mapping

Public Works · DPW-BSM

Dec 20, 2019—

Building plan review

Building Inspection · BLDG

Jan 23, 2019—

Fire prevention review

Fire Department · SFFD

Jan 29, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 4, 2020—

Street use and mapping

Public Works · DPW-BSM

Feb 4, 2020—

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2020—

Zoning review

Planning · CP-ZOC

May 20, 2021—

Building plan review

Building Inspection · BLDG

Jun 9, 2021Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 9, 2022—

Fire prevention review

Fire Department · SFFD

May 3, 2021—

Street use and mapping

Public Works · DPW-BSM

May 3, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

May 3, 2021—

Structural plan approval

Building Inspection · PAD-STR

Sep 28, 2021—

Structural plan approval

Building Inspection · PAD-STR

Sep 6, 2022Issued Comments

Zoning review

Planning · CP-ZOC

In progress—

Building plan review

Building Inspection · BLDG

Oct 29, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 21, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 19, 2026Approved

Fire prevention review

Fire Department · SFFD

In progress—

Street use and mapping

Public Works · DPW-BSM

Oct 20, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 26, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 4, 2026Approved

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$42,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Peter Scott Geissler

Geissler Engineering

EngineerC44320
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201805028044 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record