750 44th Av
San Francisco permit 201805038088 · Outer Richmond
Renovate & expand existing lower level of dwelling as follows: renovate 436 sq.ft of existing, convert 95 sq.ft of garage to dwelling, add 274 sq ft. project adds 129 sq ft deck on upper level, replace existing failing side yard stair. add second dwelling unit.
- Filed
- May 3, 2018
- Issued
- Nov 12, 2020 (30 months after filing)
- Completed
- Jun 6, 2025 (55 months after issuance)
- Review stops
- 28 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2018 | May 3, 2018 | — |
Zoning review Planning · CP-ZOC | May 3, 2018 | Aug 12, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jun 4, 2019 | Aug 12, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 13, 2019 | Aug 22, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 22, 2019 | Sep 6, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 6, 2019 | Sep 11, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2019 | Sep 19, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2019 | Sep 26, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 26, 2019 | Sep 26, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 26, 2019 | Nov 12, 2020 | — |
Addendum 1: Arch, mep, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 12, 2021 | Jan 29, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 29, 2021 | Jan 25, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2021 | Jul 7, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2021 | Oct 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2021 | Feb 16, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 29, 2021 | Oct 27, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jan 29, 2021 | Mar 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 7, 2021 | Jun 15, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2022 | Feb 7, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2022 | Feb 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2022 | Feb 11, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2022 | Feb 14, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 10, 2022 | Feb 18, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 1, 2022 | Mar 3, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 1, 2022 | Mar 3, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2022 | Mar 2, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 1, 2022 | Mar 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2022 | Mar 14, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $145,000
| Name | Role | License on permit |
|---|---|---|
| Andrew J Davis Fluid Studios | Architect | C28439 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022