793 South Van Ness Av
San Francisco permit 201805159202 · Mission
To erect 7 stories, no basement, type iii-a over i-a, 75 units residential, retail & parking. (r-2, a, m, s-1, s-2) ** maher: n/a **
- Filed
- May 15, 2018
- Issued
- Dec 5, 2018 (7 months after filing)
- Completed
- Jun 28, 2022 (43 months after issuance)
- Review stops
- 53 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 19 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 16, 2018 | May 16, 2018 | — |
Zoning review Planning · CP-ZOC | May 16, 2018 | Jun 8, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 11, 2018 | Sep 26, 2018 | — |
Fire prevention review Fire Department · SFFD | Jun 12, 2018 | Sep 25, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2018 | Nov 14, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2018 | Oct 3, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2018 | Oct 4, 2018 | — |
Development fee collection Building Inspection · DFCU | Oct 31, 2018 | Nov 19, 2018 | — |
Zoning review Planning · CP-ZOC | Nov 15, 2018 | Nov 16, 2018 | — |
Permit Processing Center Building Inspection · PPC | Nov 19, 2018 | Nov 29, 2018 | — |
Fire prevention review Fire Department · SFFD | Nov 29, 2018 | Nov 29, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Nov 29, 2018 | Dec 5, 2018 | — |
Addendum 1: Concrete substructure/superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2019 | Oct 24, 2019 | — |
Building plan review Building Inspection · BLDG | Oct 24, 2019 | Dec 6, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Nov 15, 2019 | Jan 27, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 28, 2020 | Jan 28, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2020 | Jan 30, 2020 | — |
Addendum 2: Architectural/mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 13, 2020 | Feb 13, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 13, 2020 | Feb 1, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 13, 2020 | Jun 15, 2021 | — |
Fire prevention review Fire Department · SFFD | Jun 16, 2020 | Jun 3, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2020 | Jun 18, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Sep 15, 2020 | Jan 25, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 9, 2020 | Jul 7, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2020 | Dec 9, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Jan 25, 2021 | Jul 1, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2021 | Mar 22, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2021 | Jul 7, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2021 | Jul 9, 2021 | — |
Public health review Public Health · HEALTH | Jul 9, 2021 | Jul 12, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 12, 2021 | Dec 29, 2021 | — |
Permit Processing Center Building Inspection · PPC | Dec 29, 2021 | Jan 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2022 | Jan 5, 2022 | — |
Addendum 3: Fire sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 9, 2020 | Nov 9, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 9, 2020 | Dec 10, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 11, 2020 | Dec 11, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 11, 2020 | Dec 24, 2020 | — |
Addendum 4: Fire alarm system, elevator landing & stairway-2-way communication
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 27, 2021 | May 27, 2021 | — |
Fire prevention review Fire Department · SFFD | May 28, 2021 | Jun 4, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 4, 2021 | Jun 4, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2021 | Jun 11, 2021 | — |
Addendum 5: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 7, 2021 | Apr 7, 2021 | — |
Fire prevention review Fire Department · SFFD | Apr 7, 2021 | May 12, 2021 | — |
Permit Processing Center Building Inspection · PPC | May 13, 2021 | May 14, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 14, 2021 | May 20, 2021 | — |
Addendum 6: Stormwater.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 2, 2021 | Mar 2, 2021 | — |
Plumbing plan check Building Inspection · PID-PC | Mar 2, 2021 | Mar 11, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 11, 2021 | Mar 11, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2021 | Mar 16, 2021 | — |
Addendum 7: Affordable housing documentation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2021 | Dec 29, 2021 | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $20,050,000
| Name | Role | License on permit |
|---|---|---|
| Ian J Birchall Ian Birchall & Associates | Architect | C28023 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2017