19 Miguel St
San Francisco permit 201805179370 · Glen Park
Enclose two existing decks. remodel three bathrooms
- Filed
- May 17, 2018
- Issued
- Mar 25, 2019 (10 months after filing)
- Completed
- Oct 7, 2021 (30 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 23, 2018 | May 23, 2018 | — |
Zoning review Planning · CP-ZOC | May 23, 2018 | Oct 25, 2018 | — |
Planning neighborhood notice Planning · CP-NP | Sep 6, 2018 | Oct 25, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 25, 2018 | Nov 7, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2018 | Dec 21, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 21, 2018 | Dec 26, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 27, 2018 | Jan 31, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jan 31, 2019 | Jan 31, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2019 | Mar 25, 2019 | — |
Addendum 1: Superstructure, arch, mech, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 25, 2019 | Mar 25, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 25, 2019 | Apr 18, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 18, 2019 | Apr 18, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2019 | Apr 18, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 18, 2019 | Apr 19, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2019 | Apr 22, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 23, 2019 | Apr 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2019 | Jul 23, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $125,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Rex Hardy Thomas Rex Hardy, Aia | Architect | C12683 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025