143 Laidley St
San Francisco permit 201805290365 · Glen Park
Comply with notice of enforcement 2018-002306 enf & approve as built conditions.
- Filed
- May 29, 2018
- Issued
- Dec 14, 2022 (55 months after filing)
- Completed
- Nov 1, 2024 (23 months after issuance)
- Review stops
- 18 stops across 3 departments
- Comments issued
- None
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 29, 2018 | May 29, 2018 | — |
Zoning review Planning · CP-ZOC | May 29, 2018 | Aug 30, 2021 | — |
Planning neighborhood notice Planning · CP-NP | May 4, 2021 | May 7, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 31, 2021 | Mar 14, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 9, 2021 | Apr 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2022 | Mar 25, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2022 | Mar 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2022 | Apr 18, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 29, 2022 | Dec 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2022 | Dec 14, 2022 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 12, 2024 | Feb 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 15, 2024 | Mar 27, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 15, 2024 | Apr 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 15, 2024 | Feb 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 15, 2024 | Mar 5, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 15, 2024 | Apr 2, 2024 | — |
Zoning review Planning · CP-ZOC | Feb 16, 2024 | Feb 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2024 | Apr 4, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $159,011
| Name | Role | License on permit |
|---|---|---|
| H Ruth Todd Page & Turnbull | Architect | C22714 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2013